PROJECT MANAGEMENT CONSULTANT AND SUPERVISION ERECTION AND INSTALLATION, COMMISSIONING AND STARUP OF THE ISOMERIZATION UNIT

The subject of the project is the continuous inspection of the implementation work directly at the customer's unit South Refinery company (Basra, Iraq).

reference detail image

A Joint venture technical consultant services on site and home office for mechanical completion of the unit, including management of suppliers and unit licensor UOP, pre- commissioning activities, commissioning, reactors catalyst loading and start-up of the unit with end user staff training.

Project History

2009 - 2010 - UNIS involved in design services of the unit (Electrical, Instrumentation, Telecommunication, FDS, GDS, DCS).
2016 - Supply of some items
2018 - Present - Consultant services
2023 - Plan to put unit in operation

reference detail map
End user:
Basra, Iraq
Expected completion date:
2024